- Steel
- 2,500+ T
- Sheds
- Lime, coal and lignite
- Scope
- Design, manufacture, erection
- A first
- Our first space-frame order
- Status
- In execution
The project
Stockpiles need wide, column-free cover; a space frame spans it with ball nodes and tubes that have to close without forcing.
What we made
- Detail design
- Ball nodes and tube members
- Erection
How we built it
- Submerged-arc (SAW) welding lineTubes cut to length.
- ABB robotic MIG welding cellsEnd cones welded by robot.
The first of what is now a vertical in its own right, about 10,000 T of space frames a year.
More case studies
Construction equipment · India
Access steel for batch-mix plants, five sets a month
5 sets a month
Oil & gas · Louisiana, USA
Enclosed ground flares for an LNG export terminal in Louisiana
4 enclosed ground flares
Oil & gas · Hazira, Gujarat
A 50 m enclosed ground flare chamber, delivered in 3 months
50 m high
Construction equipment · India
Access steel for batch-mix plants, five sets a month
5 sets a month
Oil & gas · Louisiana, USA
Enclosed ground flares for an LNG export terminal in Louisiana
4 enclosed ground flares
Oil & gas · Hazira, Gujarat
A 50 m enclosed ground flare chamber, delivered in 3 months
50 m high
Start a project
Send us a drawing
A project like this?
Send the drawings and an engineer will tell you how we would build it.